|
Case
Study: Hi-Ground Scaffolds and Finite Element Analysis
Finite
Element Analysis (FEA) is based on the concept that all materials
have unique properties, and thus react differently to unique loads
and forces. FEA can be used in computer programs to anticipate the
reaction of materials and product designs to forms of stress, such
as the weight of a 4-wheel ATV on its trailer.
Finite Element
Analysis is used by designers to test different materials in their
products, determining spots where the design is weak or unnecessarily
strong. For example, an airplane manufacturer could use FEA to ensure
the materials on landing gear will safely support its high-speed
impact; they could also use it to shed needless bolts on their wings,
saving expensive materials or added fuel.
Hi-Ground Scaffolds
asked the Malco Design and Deliver Group for assistance with a problem
they were having with a new drywall cart design. Though the idea
behind Hi-Ground's innovation was to add handles onto the cart in
order to provide added usability and rollover safety, the starting
point for the cart's improvements was a generic design that Hi-Ground
already marketed. The Malco D2 Group used FEA to detect and fix
the cart design problem.
"While
testing this generic design in our FEA program, we learned that
the force of a full load of sheetrock would actually push materials
on the cart past their expected failure point," said Kyle Bjork,
Chief Design Engineer. Multiple welds on that design would have
likely cracked during prototype testing, or even worse, once the
new and improved cart had already rolled out.
"Because
we hadn't yet built any physical product, we were still able to
go back into our FEA program, and start testing new designs,"
Kyle added. "Soon after, we were able to find a new solution
to adjust the amount and length of the welds, effectively eliminating
the known failure points without adding significant cost or bulk
to the cart."
Most notably,
the Malco Design & Deliver Group was able to do so within the
FEA program in a matter of hours and days, instead of the months
it would have taken to build a flawed prototype or manufacture product.
The time and cost savings were significant for Hi-Ground Scaffolds,
not to mention the added confidence they had taking their new product
to market.
|